Clients should start by visiting our web site and book an appointment to come to our showroom. On that first visit to Vima Design, one of the Vima designers takes the time to inform the customers as to what to expect during a kitchen renovation and what to look for in top quality kitchen cabinets and design. Once the customer is comfortable and interested with the Vima Design quality and process, we schedule a visit by one of Vima’s designers to the customer’s home (for potential customers this service is free). At the customer’s home, the Vima designer takes measurements, brainstorms with the customer, discusses the wish list and, most importantly, the budget. Once the budget is approved, the design work begins. Afterwards, the designer presents the customer with the design and the costs analysis, one part for the renovation work (if a referral is asked) and the other part for the kitchen cabinets including countertops. Once the customer has fallen in love with the design and the budget is respected, the last steps of final measurements and plan verification gets done and the order is made. The kitchen will be delivered and installed according to our schedule availability at that time.
Phase 1: Kitchen renovation & preparation (by the general contractor)
10-20 business days depending on size of renovation project.
Phase 2: Kitchen delivery & installation + counter measurement if necessary
2-5 days depending on the size of the kitchen.
Phase 3: Waiting time for counter production & installation
10-15 business days. A temporary countertop and sink can be installed by your contractor during the wait.
Phase 4: Kitchen completion (by the general contractor)
1-5 days depending on the work remaining.